We are progressing one of our most important growth projects to strengthen zinc production and resource conversion at Gamsberg. The Phase II expansion will double mining capacity from 4 MTPA to 8 MTPA and add a new 200 KTPA concentrator plant, taking Gamsberg’s total MIC capacity to 450 KTPA. The project is advancing towards commissioning in FY 2026-27 and stood at nearly 94% completion at the close of FY 2025-26.
The Phase II expansion will strengthen Gamsberg’s position among the leading global mining operations, while creating significant employment during construction and peak operations.
93.77%
Overall completion rate as of March 2026
We will continue to advance Phase II execution with a focus on commissioning readiness, infrastructure integration and operational ramp-up. As the project moves towards completion, the expansion is expected to add 200 KTPA of MIC, strengthen Gamsberg’s global production standing and support large-scale employment, with around 2,000 to 2,500 jobs during construction and a further 800 to 1,000 jobs during peak operations.